Metal Powder Coating - Progressive Powder Coating
New Infrared
Curing Oven at Metal Finishing Plant Increases Production by 50%
Summary
Like most metal finishing plants, Progressive Powder Coating in Mentor,
Ohio, uses a convection oven in its manufacturing process. Progressive
Powder was experiencing bottle necks in its production process because of
the time required to cure thicker pieces of metal in the convection oven.
Curing thicker metal pieces forced the plant to slow the conveyor line
speed, which reduced productivity. In an effort to save energy and improve
production, Progressive Powder installed an infrared (IR) oven in between
the powder coating booth and the convection oven on its production line. The
IR oven allowed the plant to increase its conveyor line speed and increase
production by 50%. In addition, the plant was able to reduce its natural gas
consumption, yielding annual energy savings of approximately Si54,000. With
a total project cost of S136,000, the simple payback is 2.5 years.
Company
Background
Progressive Powder Coating is a subsidiary of Buyers Products Company, a
manufacturer of products for the mobile equipment industry, including truck
and trailer
components. Buyers Products is a vertically integrated company
whose manufacturing
capabilities include forging, stamping, laser cutting,
computer numerically controlled machining, robotic welding, powder coating,
assembly, and retail-oriented packaging. Progressive Powder performs most of
the powdered metal coating for Buyers Products in its 25,000-square-foot
facility. In addition to the convection oven, Progressive Powder's plant
contains a five-stage product washing unit, a dedicated cleaning stage, an
iron phosphate stage, and an anti corrosion sealer stage.
Before the IR booster oven was installed, Progressive Powder depended on a
traditional convection oven to cure the powder coats. This curing oven is
approximately 128 feet long, with two 60-foot zones and an 8-foot
wrap-around section. This length is typical for a facility such as
Progressive's plant and is necessary so that the plant's products will have
sufficient tin1e to absorb heat at the proper curing temperature.
Project
Background
Progressive
Powder Coating worked with Dominion Power to evaluate the convection oven to
determine how to eliminate the production delays. Despite the convection
oven's length! it was unable to fully cure the thickest pieces at normal
conveyor line speeds. The conveyor line speed had to be slowed down to 4
feet per minute (fpm) for the powder coating on
thick pieces to become fully cured, which
lowered the plant's productivity, causing production bottlenecks and
scheduling problems. Because the plant's gas usage was consistently
between 1.8 to 2.4 million cubic feet per hour of operation, regardless of
the mix of products that were cured, the thinner pieces were more costly to
treat on a per-unit basis than thicker ones.
Although the line speed could be increased for thinner pieces and slowed
when thicker pieces entered the oven, plant personnel determined that this
was not optimal because the convection oven needs time for any new
temperature to stabilize before it can be used effectively. If thinner
pieces are in the oven and there is a change to thicker products, spaces
must be left on the conveyor belt to allow for the temperature in the oven
to rise and the thinner products to exit the oven. If not for the space, the
thinner pieces would be over cured or burnt and the first few thicker pieces
under cured.
In
addition, the entrance to the convection oven was more than 100 feet away
from the end of the powder-coating booth. This caused powder loss because of
the conveyor belt vibrations and convection oven turbulence, and reduced
product quality
Project
Overview
Working with Dominion Power consultants, Progressive Powder personnel
analyzed the possibility that an IR booster oven could alleviate the plant's
problems. After reviewing
the plant's production needs and various types of IR ovens, Progressive Powder
purchased and installed a 40-foot catalytic IR
oven. The plant placed the new oven between the end of the powder coating
booth and the
convection oven. To minimize
powder loss from the conveyor belt vibrations, Progressive placed the IR
oven just 12 feet beyond the powder coating booth. Because the IR oven can
reach temperatures of up to 475ºF, plant personnel realized that it could be
used to pre-gel and cure powder coatings before the pieces enter the
convection oven, thereby minimizing the amount of time they need to be in
the convection oven.
Project
Results
The
installation of the IR oven has allowed Progressive Powder's plant to
increase production and improve product quality, while decreasing energy
consumption. The IR oven can pre-gel or partially cure thicker pieces before
they enter the convection oven and can fully cure many thinner pieces. This
allows the conveyor line speed to be maintained at 6 fpm instead of 4 fpm
and has led to a production increase of just over 50Yo. In addition, because
the IR oven can pre-gel the powder coating before the piece enters the
convection oven, less powder is shaken off by the conveyor or blown off by
convection oven turbulence before gel temperature is reached. This has led
to more consistent product quality and fewer products that have to be
rejected or reworked. With the IR oven's curing ability and the improved
product quality, Progressive Powder's plant now has more flexibility in its
production scheduling.
Because
some pieces can be fully cured in the IR oven, the convection oven uses less
natural gas. The IR oven does not use blowers or fans, so the plant's
electricity consumption is unchanged from before the IR oven's installation.
However, natural gas usage is down 15.5% per piece and 6.8% per pound of
product. Overall, the Mentor plant's natural gas consumption has declined by
25%, yielding annual energy savings of $54,000. Because the project's total
cost was $136,000, the simple pay back is just over 2.5 years
Lessons
Learned
IR
heating ovens can improve energy efficiency and productivity in industrial
plants that perform process heating. In the case of Progressive Powder, the IR heat
generated by the IR oven was able to pre-gel and cure many types of
products before they entered the convection oven. This allowed the plant to
increase its production and reduce its energy consumption because pieces did
not have to spend as much time in the convection oven to become fully cured.
By experimenting on thinner products plant personnel have found they can
boost line speeds to as high as 12 fpm, and they are exploring additional
ways to fully utilize the IR oven. By optimizing the proportion of IR
heating versus convection heating that will deliver the highest efficiency,
Progressive Powder
Coatings has improved the effectiveness of its production
process.
Natural
Gas Catalytic Infrared
Natural gas catalytic infrared (IR) is a flameless heating technology that
produces a uniform, low intensity heat. A wide range of materials; including
powder paints, readily and evenly absorbs its medium- to long-wavelength
energy. The wave length of the IR light determines the temperature the
source will receive: The longer the wavelength, the lower the source
temperature. Natural gas IR heating is adjusted by using different
wavelengths of light in the IR spectrum band. The technology works by a
diffusion process in which natural gas and air meet at a catalyst sandwiched
between two layers, one of air and one of natural gas, in a counter
diffusion mode. Because radiation rather than convection or conduction
transfers heat, only the surface of the part and the powder must be heated
rather than the whole part. The IR oven has no blowers or fans like a
convection oven and thereby uses much less electricity and natural gas,
depending on product mix, than convection ovens. The technology is also
environmentally friendly and can help reduce emissions.
BENEFITS
-
Saves $54,000
annually
-
Increases production
by 50%
-
Improves product
quality
-
Reduces natural gas
consumption by 25% annually
-
Achieves a 2.5-year
simple payback
A
Best Practices Case Study from the U.S. Department of Energy View in Printer Friendly Mode

|